Camp Verde News – The Town of Camp Verde has contracted with Traffic Safety, Inc. to complete its annual roadway striping project. Work is scheduled to begin on Tuesday, May 27, 2025, and will continue through Friday, June 6, 2025.
This project involves repainting all striping on Town-maintained roadways. Residents and businesses may experience brief periods of increased noise and minor traffic disruptions while work is underway in their area.
Schedule Overview:
- May 27–30 (Daytime Work): Crews will repaint centerlines, lane lines, and edge lines.
- June 2–6 (Nighttime Work): Crews will complete stop bars, crosswalks, and turn arrows.
During this time, motorists may encounter brief delays and temporary lane or road closures. Please follow all posted signage and avoid driving or walking on freshly painted striping.
We appreciate your understanding and cooperation as we work to improve road safety and visibility in our community. If you have specific concerns—such as scheduled deliveries, construction, or accessibility needs—please contact the Public Works Department in advance, and we will do our best to accommodate.
For questions or more information, contact Martin Smith at (928) 554-0822.