ADOT SR 179 construction update for week of November 9, 2009
Sedona, AZ - (November 8, 2009) -
Work progresses on both the uphill
and downhill footings in preparation for building
the retaining walls between Morgan Wash and Canyon
Drive.

Traffic will be restricted for up to
five minutes between 7 a.m. and noon on Monday and
Wednesday as large equipment places and removes the
wall forms prior to and after the concrete wall
pour.
Bridge Work
The concrete deck pour is planned for this Tuesday
on the bridge. Traffic restrictions are not
anticipated.
Lane Line Striping
Lanes will be re-striped at the "Y" this Saturday
the 7th beginning around 7 p.m. Traffic may be
restricted through the roundabouts.
|
Sedona Arizona News, Jobs, Tourist Info, Classifieds, Forums - Sedona.biz
|
Median Curb and Gutter
The median curb and gutter north of Chapel, and in
the Oak Creek Cliffs to Juniper Trail area, will be
completed this month.
Saturday Work
The contractor will be working Saturdays through the
end of the year except for holiday weekends.
Use Your Turn Signal in Roundabouts
When approaching a roundabout, others need to know
where you’re going, and drivers should use their
turn signals just as they would when approaching a
traditional intersection. Please use your turn
signals to let other drivers know your intentions if
you are turning to the right or the left (and not
going straight through). |